SPENCER/EAST BROOKFIELD – David Fontaine, CEO of Fontaine Brothers Inc. gave a presentation about general requirements funding as the David Prouty High School building project continues to wind down.
At its October meeting, the building committee approved change orders totaling $563,288, with the bulk of that amount ($545,935) going to the general requirement allowances Fontaine described.
Fontaine explained general requirements pay for the services and temporary facilities needed to operate a job site. Examples would be for weather protection and safe daily operations and site support such as cleaning debris and dumpsters as well as access and lifting (staging, hoisting, temporary barriers).
He said Fontaine tried to “lock in,” set prices with subcontractors as much as possible but factors like unpredictable weather, undefined scope/quantities and commodity fluctuations cannot be fully fixed.
Some of the larger cost increases were for temporary heat/weather conditions ($134,342) and cleaning and labor ($190,523).
Fontaine said fuel use and price both matter because longer heating periods also add rental and labor costs. He said the total general requirements replenishment amounted to $540,530 with bonds and insurance at $5,405 comprising the rest.
Architect Kristian Whitsett of Whitsett Jones described a handful of other change orders including $2,176 for locks changes at wheelchair lifts; $1,746 for modifications to the auditorium’s floating ceiling; and $5,578 for intrusion keypad additions, to name a few.
In other business, the committee approved $3,973,588 in invoices. Nick Pimentel of owner’s project manager (OPM) Colliers noted that contractually, the project has been done for six weeks and he is hoping the remaining “punch list,” items are done by the holidays.
He said they are trying to finish commissioning with heating, ventilation and air conditioning (HVAC) systems and tend to minor issues like a few cracked tiles.
The $680,000 remaining in the project is “scattered across everything under the sun,” Pimentel said and can be moved to line items where needed.
Tom Wolfenden of Fontaine Brothers said other remaining punch list items include ongoing owner’s training for things like electric vehicle (EV) charging and automatic temperature control as well as installation of three graphic displays for stairwells.
Ninety-six percent of the architect/engineer items are done while 66% of administrative/staff activity is finished, with the rest planned for off hours or coordinated with administration in unoccupied spaces, according to Wolfenden.
Building Committee member Ralph Hicks asked where all the plaques and monuments “obligated to be salvaged,” were, including memorials for students who died. Hicks said he would come over because he knows where these things should be put back and he wants to ensure everything is returned to where it should be.
Interim Superintendent Gary Suter was asked to research the whereabouts of the items and where they should be re-installed. Wolfenden said he would review the situation as he is aware of storage in the boiler room, garage, etc.
Hicks also asked about plans to satisfy abutters’ concerns about weeds and brush near the baseball field slope adjacent to Greenville Street.
Whitsett and chair Michael Ethier replied plans involve removing and grubbing existing vegetation and putting in new shorter grass seed, probably in the spring, because to do it earlier would likely cause erosion problems.
In addition, Ethier announced that an open house would be held on November 12 from 5 p.m. to 7 p.m. so that members of the public can see first hand the results of the $116 million school project.
The next David Prouty High School Building Committee meetings on Zoom will be November 19 and December 17.